On 28 November, the International Tribunal for the Law of the Sea (ITLOS) rejected Argentina’s request for provisional measures in its dispute with the United Kingdom over the Sea Lion oil project. The vote was 18 to 3. The tribunal did not order a temporary halt to the work and did not determine sovereignty over the Falkland Islands (Malvinas).

What the figures say
Decision and timetable are distinct
| Date or result | Meaning |
|---|---|
| 18 to 3 | Argentina’s request for provisional measures rejected |
| 21 March 2027 | Earliest drilling date according to the UK’s assurance |
| March 2028 | Earliest extraction date according to the UK’s assurance |
Paragraphs 129–134 of the Order; comparison by SYGNAŁ.
Open the source →Argentina sought to stop work connected to the Sea Lion oil project in the South-West Atlantic until a separate arbitral tribunal could be constituted. The Hamburg tribunal’s decision today concerns provisional measures. Its reasoning draws a distinction that matters for the wider dispute: jurisdiction under the law of the sea does not automatically provide authority to decide territorial sovereignty.
What Argentina asked the tribunal to do
According to ITLOS, Argentina filed its request on 13 October. Public sittings took place on 10 and 11 November. Argentina asked for steps including a halt to new drilling and the installation of production infrastructure connected with Sea Lion. It also sought protection of its claimed rights over resources and the marine environment, and requested that the UK refrain from measures that might aggravate the dispute. The United Kingdom asked the tribunal to reject the requests.
ITLOS examined whether the provisions of the United Nations Convention on the Law of the Sea invoked by Argentina provided an apparent, preliminary basis for the jurisdiction of a separate arbitral tribunal. In paragraph 129, it concluded that the invoked provisions did not appear to provide such a basis. It therefore did not need to examine the other conditions for prescribing provisional measures.
In paragraph 134, the tribunal rejected the application by 18 votes to 3. The refusal of provisional measures is narrow in scope. For investors, it means the requested prohibition has not been imposed at this stage, not that a new permission to exploit the field has been granted. The ruling does not award sovereignty over the islands to either country.
The timetable recorded in the Order
The tribunal recorded the United Kingdom’s assurance that drilling would not begin before 21 March 2027 and extraction would not start before March 2028. The UK also said no further licences would be issued as its licensing regime was suspended. These statements appear in paragraph 130.
The distinction is important for the project timetable. The dates were assurances given by one party, not an ITLOS order requiring operations to start, and not a guarantee that the operator will meet those dates. The Order does not establish that extraction is already under way.
What remains open
The tribunal found that deciding the claims as presented would require identifying which country holds the rights of a coastal state in the maritime areas concerned. That would involve determining territorial sovereignty over the Falkland Islands, which Argentina calls the Malvinas. ITLOS considered that this fell outside the scope of deciding the interpretation or application of the law-of-the-sea convention as framed in the dispute.
The Order expressly leaves open the definitive jurisdiction of the separate arbitral tribunal, the admissibility of Argentina’s claims and their merits. In paragraphs 131–133, ITLOS encouraged the parties to cooperate in establishing the arbitration swiftly and recalled the applicability of the convention in the maritime areas at issue.
For the oil market, the next observable milestones are the constitution of the arbitral tribunal and any documented changes to the project schedule. Subsequent records may clarify whether the legal dispute affects timing and costs. Today’s decision provides neither a basis for forecasting oil prices nor a final resolution of the dispute between the two countries.
Sources
- ITLOS Case No. 37, Order of 28 November 2026
The 18–3 decision, prima facie jurisdiction assessment, paragraphs 129–134 and UK assurances.
- ITLOS Press Release 406
Argentina’s requests and the tribunal’s reasoning.
- House of Commons Library: UK-Argentina tensions on the Falkland Islands and oil
Background to Sea Lion and the separate arbitration.
First publication; no recorded corrections.